Minsk
Construction of outpatient clinic at Minsk Oncology Center ahead of schedule
The building is already ready for interior finishing and installation of medical equipment. Installation of window units and insulation of the external envelope has been completed.
About 95% of gypsum board partitions have been installed inside the building. Landscaping of the adjacent territory is planned for August.
✔️ Minskach • Subscribe