Metro builders resume movement of TBM 'Alesya' toward Perespa station
After scheduled preventive maintenance, the tunnel boring machine 'Alesya' has resumed its course toward the Perespa station. The complex has returned to its designated trajectory. There are 56 meters left to the end of the route — equivalent to 40 tunnel rings. So far, 1,198 rings have been installed since the start of construction.